Why the estimate carries a structured $247,943 risk pool instead of a flat percentage.
Schedule & Phasing Risk
$92,000
Night work, lane closures and productivity loss.
Conservative production rates were used for demolition, trucking and paving under constrained
traffic windows. Change-of-sequence and erosion risk were captured in this bucket.
Traffic & Safety Risk
$68,000
Work-zone incidents, detours and MOT changes.
Covers potential redesign of maintenance-of-traffic, added flagging hours, temporary barriers
and additional safety measures requested by the owner.
Geotechnical & Quantities Risk
$87,943
Soil behavior, unsuitable material and quantity growth.
Based on the geotechnical report and earthwork assumptions, this amount protects against
under-cut, soft spots, moisture conditioning and unanticipated subgrade repair.